HAHarvey Walden
2 weeks ago2026 Paving Project Schedule Update
Stark Paving, the contractor performing the road improvements, is expected to begin work in the Village in early October. The current schedule, weather permitting, is:
Elmhurst Parkway (124th-Notre Dame)
10/6–10/19: Road preparation and manhole adjustments
10/20–10/24: Paving
10/24–10/27: Restoration
Fairfax Drive (Gremoor-Wrayburn) & Cloverhill Road (North-Wrayburn)
10/9–10/22: Road preparation and manhole adjustments
10/23–10/24: Paving
10/28–10/29: Restoration
Hollyhock Lane (Wrayburn-Dunwoody) / Notre Dame Blvd (Walnut-Gremoor)
10/9–10/22: Road preparation and manhole adjustments
10/23–10/24: Paving
10/28–10/29: Restoration
Residents will receive additional updates as work progresses. Please expect minor delays during construction and avoid the work areas when possible. If access to your home is temporarily blocked, a crew member will be available to assist. On paving days, please avoid driving on the new asphalt whenever possible. If you need to pass through the area, drive slowly, follow crew instructions, and avoid sharp turns or sudden braking.
Thank you for your patience and cooperation! It would be helpful if you have any questions about the project, please email Public Works Director Richard Paul Jr. at [email protected]. Those who live in the project area may wish to email the Director to be added to a separate notification list for pertinent project updates involving access to-and-from properties.