May 1, 2026 Construction Update - Park Garden Parking Lot Reconstruction
May 1, 2026 Construction Update - Park Garden Parking Lot Reconstruction Majority of the removals are complete Concrete work in process Storm water infrastructure will be completed early May Irrigation and landscaping started Grading and aggregate base placement early May Paving mid-May Cleanup, restoration, pavement markings, signage and pay station installation to follow paving Anticipating completion Memorial Day weekend Thank you for your understanding and patience throughout the construction process. If you have any questions or would like additional information regarding this project, please contact the Construction Engineer, Matt Miller or Director of Public Works, Jason Fate at 231-347-2500.