Howard & East Mitchell Street Reconstruction Project Update
May 1, 2026 Construction Update - Howard & East Mitchell Street Reconstruction
May 1, 2026 Construction Update - Howard & East Mitchell Street Reconstruction Sanitary sewer main replacement complete Water main replacement will be complete early May Storm sewer replacement will be complete early May Intersection planter removed and replaced Majority of the removals are complete Traffic signal rewiring work started Concrete sidewalk and curb work to start early May Sidewalk and intersection decorative brick work to follow concrete placement Anticipating completion mid- June Thank you for your understanding and patience throughout the construction process. If you have any questions or would like additional information regarding this project, please contact the Construction Engineer, Matt Miller or Director of Public Works, Jason Fate at 231-347-2500. Click here to review street detour map.